Documentation of High Temperature Fighting in the Third Bid Section of Airport Road Rapid Renovation Project
The publisher£ºczszjs    Release time£º2019-09-16    Hit£º15357

 As the saying goes, "The summer solstice lasts for several volts, and the June volts burn fiercely." Feng Jicai, a famous writer, once summarized the taste of "summer" with "bitterness" and wrote down his prose "bitter summer". It is in the process of tasting the "bitter summer" that the three tenders of our airport road rapid transformation project created a group of "Changzhou politicians" who are not afraid of hardship, sweating like rain and overcoming hardships, to achieve the project target ahead of schedule. Favorable conditions.

This year's hot weather is not the same as usual, commonly known as dry yellow plum. So the project department adjusts the response plan in time. With "change" and "wisdom" to plan and formulate high-temperature construction plans and countermeasures, the following main aspects of work have been done:
1. Safe handover of high-temperature construction technology should be "early, fine and solid". As early as the implementation of the "Safety Month" work, the project department put the requirements of high-temperature construction into the inspection and assessment in advance, and formulated the pre-plan measures in advance to ensure the normal and planned high-temperature construction.
Second, adhere to "people-oriented" and ensure the construction force. The project department has conducted two investigations on the physical fitness of the construction personnel on site, organized four inspections for the construction personnel, effectively checked out the inappropriate high temperature workers to immediately remove their posts, and timely enriched their strength, which not only avoided the hidden dangers of safety accidents, but also ensured the normal operation of production and construction.
3. Strictly reiterate construction safety rules and regulations, and carry out targeted safety education in high temperature construction. In high temperature weather, with the increase of safety risk factor of open-air operation, the project department organizes high-altitude workers to conduct centralized safety education, puts forward key precautionary requirements and corresponding measures for safety work in high temperature weather, formulates management penalty regulations, and strictly handles illegal operations.
4. Actively do a good job in logistic support. The project department carries out activities to send caring water cups to workers and publicize the excellent tradition of "municipal iron army" in overcoming difficulties. The project department requires technicians to take the lead in guarding the site. Salt, soda and purified water must be adequately supplied at the site of cast-in-situ box girders in each work area. The canteen meals should be improved. Air conditioning should be installed in all the dormitories to ensure the rest quality of workers.
"Everyone is hot and bitter, and I love the long summer." The staff of the project department are determined and confident to complete all construction tasks in advance with high quality and quantity, so as to make the airport road rapid transformation project open to traffic ahead of time, and create brilliant achievements for the brand of "Changzhou municipal government"!
¡¡
¡¡

Print this page || Close the window

Jiangsu province Changzhou City Blue Ocean 158 North Road| Zip code£º213017 | Telephone£º0086-0519-85501558 |¡¡Fax£º0086-0519-85501558 |¡¡E-mail£ºczsz@czszjt.com

Copyright © CHANGZHOU MUNICIPAL ADMINISTRATION CONSTRUCTION ENGINEERING CO.,LTD.  ËÕICP±¸12078434ºÅ-1   Technical support:Public science and technology